Document ID: OG-WIN-PROD-PREOP-CHK
Version: 1.0
Last Change Date: 2026-02-26

WIN Execution Guide — Pre-Operation Readiness Verification

Non-Authoritative WIN Execution Guide Notice
This WIN Execution Guide supports execution of applicable Family Pack controls. Authority for control intent and requirements remains solely with the governing Family Pack. This document does not create, modify, or interpret controls.

Purpose

To support structured verification of equipment readiness, line clearance, documentation control, material status, and environmental conditions prior to initiating a production batch.

Scope

Applies to all production lines and equipment prior to batch start, including startup, changeover, and restart following interruption.

Section 6 — AA (Auditable Artifacts)

AA-PROD-PREOP-CHK — Pre-Operation Readiness

Auditor focus: Production does not begin without documented readiness.

QC-REQ Anchor: QC-OPS-001, QC-ENV-002


Section 7 — WIN (Work Instructions / Control Requirements)

WIN-PROD-PREOP

Stop-Execution Condition:

Control outcome: Production does not begin without verified readiness.

Process: Production (PROD)
Business Process Owner: Production BPO
Primary Systems / Forms: PREOP-CHK-01 (or equivalent readiness log)

BPO-Owned Execution Zone — Operational Step Sequence

Pre-operation readiness verification is performed and documented before initiating any batch manufacturing activity. All defined readiness criteria must be satisfied prior to batch start.

Step 1 — Verify Equipment Cleanliness and Readiness

Step 2 — Confirm Line Clearance

Step 3 — Verify Approved MMR and Controlled Documents

Step 4 — Confirm Material Identity and Status

Step 5 — Confirm Environmental Conditions

Step 6 — Document Readiness Prior to Batch Start

Stop-Execution Principle

If line clearance is incomplete, equipment is not suitable, incorrect/outdated MMR is identified, or environmental limits are exceeded:

STOP — DO NOT START BATCH — ESCALATE — DOCUMENT
Authority Reminder
This document supports execution only and is non-authoritative. The governing Family Pack remains the sole source of control intent and requirements.