Master Manufacturing Record – Encapsulation Module

SECTION 1: Reference Documents

Enter the Primary Jira Work Item. Product and batch information will automatically populate from the Jira record and cannot be edited within this document.

ORDERS-

This section identifies the governing documents and system records used during execution of the Filling Encapsualtion stage. Product requirements, formulation details, and batch execution instructions are maintained within their respective systems of record, including the Product Specification, Approved Formula, and ERP-generated Filling Encapsulation Batch Record. This Master Manufacturing Record defines the approved manufacturing procedure. Authoritative product and batch data must be obtained from the controlled source documents referenced in this section.


1.2 Core Document Sources

The following controlled documents and system records provide the authoritative product and batch information required for execution of this procedure.

Product Specification ID:
Approved Formula ID:
MMR ID:
Wherefour Batch Report ID(s):

1.3 Encapsulation Readiness

The following information is automatically populated from the Jira order and provides the operational context for the manufacturing batch.

Encapsulation operations may begin only when the Approved Manufacturing Formula is in Approved status and this Master Manufacturing Record (MMR) has been reviewed and approved by Quality Assurance within the Quality Management System.

Formula Status:
Customer Name:
Customer Order:
Finished Good Product Name:
SNL Lot:
Wherefour Work Order:
SNL WIP SKU:
Batch Weight (Kg):


1.4 QU GATE

Quality Unit authorization confirms that all required core documents are present and the Manufacturing Formula is in Approved status before Encapsulation operations may begin.

QU Gate Decision:
Evaluating QU Gate...


1.5 QC Requirements Applicable to Encapsulation

Identifies the Quality Control requirements governing environmental conditions, equipment verification, material eligibility, and blend uniformity controls applicable to this manufacturing stage.

Capsule Fill Control

Encapsulation operations introduce previously verified and released blend material into capsule shells in accordance with the approved Master Manufacturing Record (MMR) and product specifications maintained within the Quality Management System.

Capsule fill weight, capsule shell specification, and in-process weight verification are controlled according to the approved manufacturing instructions to ensure dosage uniformity and consistent finished product quality.

QC Requirement Applies To
QC-ENV-002 – Production Environmental Conditions Section 2 – Environmental Requirements
QC-ANL-002 – Instrument & System Suitability (Timers / Measurement Systems) Section 4 – Equipment & System Verification
QC-MAT-004 – Material Storage & Handling Acceptance Section 5 – Component Transfer & Staging
QC-PRO-001 – Process Control & Uniformity Assurance Section 6 – Blending Parameters & In-Process Verification

1.6 Batch Production Record Execution

Execution of the encapsulation operation must be documented in the Encapsulation Batch Production Record generated for the specific manufacturing Work Order.

The Batch Production Record defines the capsule product configuration, blend lot identification, capsule shell specifications, equipment configuration, and processing parameters required for execution of this procedure.

Operators must follow the instructions contained in the Master Manufacturing Record together with the formulation, component details, and processing parameters defined in the Encapsulation Batch Production Record for the specific Work Order.

All blend lot identification, capsule shell lot numbers, processing parameters, equipment identifications, operator identifications, and verification signatures must be recorded in the Batch Production Record at the time the activity is performed.


SECTION 2: Facility Environmental Requirements

Environmental conditions during capsule filling operations must comply with the facility environmental monitoring requirements defined in QC-ENV-002 – Production Environmental Conditions.

The environmental operating limits listed below are controlled by the Quality Management System and represent the validated operating limits for the manufacturing area where encapsulation operations are performed.

These limits are not defined by this Master Manufacturing Record and must not be modified within this document.

Product-specific manufacturing instructions may define narrower operating ranges within these limits. Such requirements must be documented in the Process Control Parameters section.

Under no circumstances may environmental conditions exceed the facility limits defined in QC-ENV-002.

Parameter Facility Operating Limit Action if Not Met Reference
Temperature 64–77 °F Stop capsule filling activity, notify the Quality Unit, document the deviation, and resume operations only after Quality Unit authorization. QC-ENV-002
Relative Humidity 30–60 %RH Stop capsule filling activity, notify the Quality Unit, document the deviation, and resume operations only after Quality Unit authorization. QC-ENV-002
Area Cleanliness Encapsulation area verified clean and line cleared prior to operation Do not proceed. Clean per approved sanitation SOP, re-verify area readiness, and document verification in the Batch Production Record. Cleaning SOP

SECTION 3: Process Control Parameters

The following process parameters represent the standard operating conditions for capsule filling operations during the Encapsulation stage.

If the Product Specification defines different requirements for a specific product, the Product Specification Override column must be used to document the approved requirement.

Parameter Default Process Requirement Product Specification Override Reference
Target Capsule Fill Weight As defined in the approved formulation and product specification Approved Formula / Product Specification
Capsule Size Capsule shell size must match the size specified in the approved product specification Product Specification
Average Fill Weight Control Maintain average fill weight within ±7.5% of the target fill weight QC-PRO-001 / Product Specification
In-Process Weight Check Frequency Verify capsule fill weight at intervals specified in the Master Manufacturing Record throughout encapsulation operations QC-PRO-001 / Master Manufacturing Record
Capsule Fill Weight Sample Size Sample size used to determine average fill weight must be equivalent to one finished unit (one bottle) of capsules unless otherwise defined in the product specification QC-PRO-001 / Product Specification

Encapsulation Material Handling

Released blend material must be transferred into the capsule filling equipment using clean, verified containers and staging procedures defined in the Master Manufacturing Record.

Capsule shells and blend material must be clearly identified with material name, lot number, and material status prior to use in encapsulation operations.

Material staging must occur only in the designated manufacturing staging area prior to capsule filling operations.


SECTION 4: Equipment Requirements

The following equipment is required for execution of the Encapsulation stage.

Equipment must be suitable for use, clean where applicable, and within required calibration or verification status prior to capsule filling operations.

Equipment readiness verification must be completed in accordance with SOP-PROD-PREOP – Pre-Operation Readiness & Line Clearance prior to performing encapsulation equipment verification or capsule filling activities.

Specific instrument and system suitability requirements are defined in QC-ANL-002 – Instrument & System Suitability.

Equipment identification and readiness verification results must be recorded in the Batch Production Record (BPR) or in the controlled execution record associated with this manufacturing batch.

4.1 Required Equipment and Utensils

The following equipment and utensils are approved for use in the Encapsulation stage when suitable for the intended operation.

Equipment / Utensil Requirement Reference
Capsule Filling Machine Capsule filling equipment must be clean, suitable for use, and verified ready for operation prior to encapsulation activities. Equipment Cleaning Verification SOP
Capsule Filler Controls / Counters Equipment controls, counters, timers, and operational indicators must be verified functional prior to operation. QC-ANL-002 – Instrument & System Suitability
Capsule Feed System / Hoppers Material contact surfaces must be clean, intact, and suitable for product contact. Equipment Cleaning Verification SOP
Capsule Orientation / Separation System Capsule orientation system must be verified operational to ensure proper capsule alignment prior to filling. Equipment Operating Procedure
In-Process Weighing Scale Scale used for in-process capsule weight verification must be within calibration status and verified suitable for use. QC-ANL-002 – Instrument & System Suitability
Capsule Collection Containers / Liners Containers used for encapsulated product collection and staging must be clean, intact, and suitable for product contact. Equipment Cleaning Verification SOP

4.2 Equipment Identification Record

Record the actual equipment assets used during execution of this Encapsulation operation. Asset identification must correspond to the equipment used for the manufacturing batch.

If additional equipment is used, add the information in accordance with approved documentation practices before finalization of the record.

Asset ID Equipment Name

Equipment that is damaged, visibly contaminated, or outside calibration or verification status must not be used.

Notify the Quality Unit and follow the established deviation procedures if required.


SECTION 5: Line Clearance

5.1 Line Start Authorization

Prior to initiation of manufacturing activities, a qualified individual must perform a Line Start verification confirming that the manufacturing area, equipment readiness, environmental conditions, and required documentation are acceptable for execution of the Encapsulation operation.

Line Start verification confirms that the manufacturing environment complies with the requirements defined in this Master Manufacturing Record (MMR) and that the production area is suitable for the current manufacturing batch.

Line Start authorization is documented within the approved electronic quality system. Manufacturing activities may begin only after Line Start verification has been completed and authorization has been granted by the Quality Unit.

Evidence of Line Start authorization is maintained within the electronic system and referenced in the associated Batch Production Record (BPR).

Execution Requirement Encapsulation activities must not begin until Line Start Authorization and Encapsulation Line Clearance have been completed and documented in the Batch Production Record.

5.2 Encapsulation Line Clearance Procedure

Prior to beginning the Encapsulation operation, the capsule filling area must be verified as clear of materials, components, equipment, labels, documentation, and waste associated with previous manufacturing operations.

Line clearance ensures that only materials and equipment required for the current manufacturing batch are present in the encapsulation area and prevents cross-batch mix-ups, contamination, and documentation errors.

Completion of line clearance must be documented in the Batch Production Record (BPR) prior to initiation of encapsulation activities.

Standard Procedure

  1. 5.2.1 Verify that the encapsulation area is free of materials, components, documentation, labels, and equipment associated with previous manufacturing operations.
  2. 5.2.2 Remove all unrelated materials, containers, labels, documentation, and waste from the encapsulation area.
  3. 5.2.3 Verify that capsule filling equipment, hoppers, contact surfaces, and utensils intended for use are empty, clean, and suitable for product contact.
  4. 5.2.4 Confirm that all equipment required for the encapsulation operation is present, properly identified, clean where applicable, and within required calibration or verification status.
  5. 5.2.5 Verify that only materials required for the current batch, identified in the approved Batch Production Record and released for use, are present in the encapsulation area.
  6. 5.2.6 Record completion of line clearance in the Batch Production Record prior to initiation of encapsulation activities.
  7. 5.2.7 Where required by the Batch Production Record or Quality procedures, a second qualified individual must verify completion of line clearance prior to beginning the encapsulation operation.
Special Instructions / Step-Specific Clarifications (Optional)

SECTION 6: Encapsulation Equipment Verification Procedure

Encapsulation equipment used during capsule filling operations must be verified prior to use to ensure the equipment is suitable for the intended manufacturing activity and capable of operating within the required process parameters.

Verification requirements are governed by QC-ANL-002 – Instrument & System Suitability.

Verification results must be documented in the Batch Production Record (BPR) prior to initiation of encapsulation activities.

6.1 Capsule Filling Equipment Verification

Prior to loading blend material and capsule shells, the capsule filling equipment must be verified to confirm proper operation and readiness for manufacturing use.

Equipment readiness must be verified in accordance with SOP-PROD-PREOP prior to performing encapsulation equipment verification.

Standard Procedure

  1. 6.1.1 Verify that the capsule filling machine identification matches the equipment specified in the Batch Production Record.
  2. 6.1.2 Confirm that equipment cleaning verification has been completed and that all product contact surfaces are suitable for product contact.
  3. 6.1.3 Inspect the capsule filling machine, hoppers, and contact surfaces to ensure they are clean, properly assembled, and free from visible residue or foreign material.
  4. 6.1.4 Verify that capsule filling controls, counters, and operational indicators are functional.
  5. 6.1.5 Confirm that capsule size components, tooling, and machine configuration are appropriate for the product specification.
  6. 6.1.6 Record the equipment identification and verification results in the Batch Production Record prior to initiation of encapsulation activities.
  7. 6.1.7 If equipment verification fails, remove the equipment from service, notify the Quality Unit, and do not proceed with encapsulation activities until the issue has been investigated and resolved.

6.2 In-Process Weighing System Verification

The weighing system used for capsule fill weight verification must be confirmed suitable for use prior to performing in-process weight checks.

Standard Requirement

  1. 6.2.1 Confirm that the scale used for in-process capsule weight verification is within calibration status.
  2. 6.2.2 Verify that the scale is functioning properly prior to use.
  3. 6.2.3 Record the scale identification and verification status in the Batch Production Record prior to performing in-process weight checks.
Special Instructions / Step-Specific Clarifications (Optional)

SECTION 7: Encapsulation Material Verification

Materials used during the Encapsulation operation must correspond to the materials specified in the approved Batch Production Record (BPR) for the current manufacturing batch.

Blend material used for encapsulation must originate from an approved Blending operation and must have been verified and released by the Quality Unit in accordance with applicable Quality Control procedures.

Capsule shells must meet the approved product specification and must be verified as suitable for use prior to initiation of encapsulation activities.

Standard Requirement

  1. 7.1 Verify that the blend material staged for encapsulation corresponds to the blend lot identified in the approved Batch Production Record for the current manufacturing batch.
  2. 7.2 Confirm that the blend container labeling includes the blend lot number, product identification, and material status indicating release for use.
  3. 7.3 Verify that capsule shells staged for encapsulation correspond to the capsule specification defined in the approved product specification.
  4. 7.4 Confirm that capsule shell containers are properly labeled and include capsule size, lot number, and material identification.
  5. 7.5 Materials that cannot be positively identified or that do not match the Batch Production Record must not be used during encapsulation operations.
  6. 7.6 If discrepancies are identified, stop the operation and notify the Quality Unit for investigation prior to continuing encapsulation activities.

SECTION 8: Encapsulation Execution Instructions

Encapsulation instructions for the specific manufacturing batch are generated from the approved product configuration and process parameters defined within the Quality Management System and provided as a controlled execution artifact associated with the Batch Production Record (BPR).

The encapsulation instruction artifact may be provided as either:

The instruction artifact is derived from approved product specification data, encapsulation process parameters, and applicable Quality Control requirements maintained within the Quality Management System.

Standard Requirement

  1. 8.1 Verify that the encapsulation instruction artifact corresponds to the correct manufacturing batch and approved product specification.
  2. 8.2 Confirm that the instruction artifact includes the approved capsule size configuration, target fill weight, encapsulation parameters, and applicable process controls.
  3. 8.3 Execute the encapsulation operation in accordance with the instructions provided in the controlled artifact.
  4. 8.4 Record execution results and required process data in the Batch Production Record (BPR).
  5. 8.5 If the instruction artifact is unavailable, incomplete, or inconsistent with the Batch Production Record, the encapsulation operation must not proceed and the Quality Unit must be notified.

SECTION 9: Theoretical Encapsulation Yield

The theoretical encapsulation yield for the manufacturing batch is derived from the approved formulation and target capsule fill weight defined in Appendix A – Approved Formula.

The expected number of capsules to be produced is calculated using the approved blend quantity and target fill weight. Actual capsule yield and reconciliation values must be recorded in the Batch Production Record (BPR) upon completion of encapsulation operations.

Material discrepancies identified during reconciliation must be reported to the Quality Unit and investigated in accordance with applicable Quality procedures prior to continuation of subsequent manufacturing steps.

Parameter Reference
Total Theoretical Capsule Quantity Derived from Appendix A – Approved Formula and Target Fill Weight
Actual Capsules Produced Recorded in the Batch Production Record (BPR)
Acceptable Yield Range Defined by formulation tolerance and applicable process specifications

Standard Requirement

  1. 9.1 Upon completion of encapsulation, determine the total number of capsules produced for the batch.
  2. 9.2 Compare the actual capsule quantity against the theoretical capsule quantity derived from the approved formulation and target fill weight.
  3. 9.3 Record the reconciliation results in the Batch Production Record (BPR).
  4. 9.4 If reconciliation results fall outside the acceptable yield range, notify the Quality Unit and follow the applicable deviation procedures.

SECTION 10: Encapsulation Reconciliation

Encapsulation reconciliation ensures that all materials used during the encapsulation operation are properly accounted for and that the total number of capsules produced corresponds to the theoretical encapsulation yield defined in Section 9.

Reconciliation must be completed upon completion of encapsulation operations and prior to transfer of the encapsulated product to the next manufacturing step.

Parameter Description
Theoretical Capsule Quantity Total expected capsule quantity derived from Appendix A – Approved Formula and target fill weight.
Actual Capsules Produced Total number of capsules produced during encapsulation.
Rejected Capsules Capsules removed during in-process inspection or machine rejection.
Remaining Blend Residual blend material remaining after completion of encapsulation.
Variance Difference between theoretical capsule quantity and reconciled capsule output.

10.1 Encapsulation Reconciliation Procedure

Encapsulation reconciliation must be performed after completion of encapsulation operations and prior to progression of the manufacturing batch to the next processing step.

Standard Procedure

  1. 10.1.1 Determine the total number of capsules produced during the encapsulation operation.
  2. 10.1.2 Record the quantity of rejected capsules identified during in-process inspection or machine rejection.
  3. 10.1.3 Determine the quantity of remaining blend material after completion of encapsulation.
  4. 10.1.4 Compare the reconciled capsule quantity, including rejected capsules and remaining blend material, against the theoretical capsule quantity defined in Section 9 to confirm material accountability.
  5. 10.1.5 Record reconciliation results in the Batch Production Record (BPR).
  6. 10.1.6 If reconciliation results fall outside acceptable limits, stop progression of the manufacturing batch and notify the Quality Unit for investigation.
  7. 10.1.7 Where required by the Batch Production Record or Quality procedures, reconciliation results must be reviewed and verified prior to transfer of the encapsulated product to the next manufacturing step.
Special Instructions / Step-Specific Clarifications (Optional)

SECTION 11: Acceptance Criteria

Parameter Acceptance Criteria
Blend Material Verification Blend material corresponds to the Batch Production Record, is properly labeled, and has been released for use by the Quality Unit.
Capsule Shell Verification Capsule shells correspond to the approved product specification, are properly labeled with capsule size and lot number, and are approved for manufacturing use.
Encapsulation Equipment Verification Capsule filling equipment and weighing systems are verified according to QC-ANL-002 and documented in the Batch Production Record.
Encapsulation Execution Encapsulation is performed in accordance with the controlled execution instructions associated with the Batch Production Record.
In-Process Fill Weight Control Average capsule fill weight is maintained within ±7.5% of target fill weight and verified according to QC-PRO-001 and defined in-process control procedures.
Encapsulation Yield Actual capsule quantity is within the acceptable yield range defined in Section 9 and the Approved Formula.
Encapsulation Reconciliation Reconciliation is completed and documented in the Batch Production Record prior to transfer to the next manufacturing step.

SECTION 12: Deviation Handling

A deviation must be initiated whenever manufacturing activities do not comply with the requirements defined in this Master Manufacturing Record, the Product Specification, or applicable Quality procedures.

Examples of events requiring deviation documentation include, but are not limited to, the following:

Deviations must be documented in the Quality Management System and evaluated by the Quality Unit prior to continuation of manufacturing activities.

12.1 Deviation Response Procedure

If a deviation or nonconformance occurs during the encapsulation operation, the following actions must be performed.

Standard Procedure

  1. 12.1.1 Immediately stop the affected manufacturing activity and secure the process to prevent continuation of the operation.
  2. 12.1.2 Segregate and clearly identify any affected materials to prevent inadvertent use in manufacturing.
  3. 12.1.3 Notify the Quality Unit of the deviation or nonconformance.
  4. 12.1.4 Initiate a deviation record in the Quality Management System in accordance with the established deviation management procedure.
  5. 12.1.5 Document the deviation and any affected materials or equipment in the Batch Production Record (BPR).
  6. 12.1.6 Manufacturing activities must not resume until the deviation has been reviewed, investigated where required, and dispositioned by the Quality Unit, and authorization to continue has been documented.
Special Instructions / Step-Specific Clarifications (Optional)

SECTION 13: Data Integrity Requirements (ALCOA+)

All data generated during execution of this procedure must comply with ALCOA+ data integrity principles and applicable Quality Management System requirements.

All records generated during manufacturing activities must be:

Entries in the Batch Production Record must be recorded at the time the activity is performed. Data must not be backdated or recorded in advance of the activity.

Corrections to recorded information must be made using a single line strike-through so that the original entry remains legible. Corrections must include the initials of the person making the correction, the date of correction, and the reason for the change where required by applicable procedures.


SECTION 14: Electronic Records and Signatures

Electronic systems used in the execution and documentation of this Master Manufacturing Record (MMR) must comply with applicable electronic record and electronic signature requirements where regulated manufacturing records are generated or maintained.

Electronic records generated during manufacturing execution are considered official manufacturing records when created, maintained, and approved within validated electronic systems operating under approved procedures.

System Purpose Control Requirement
ERP / Inventory System Generation of Work Orders and Batch Production Records System access control, user authentication, and audit trail capability required
Quality Management System (Jira) Document approval, deviation management, and quality oversight Electronic approval workflow with traceable user identity and audit trail
Document Control System Storage, revision control, and distribution of MMR documents Controlled access, version history, and document approval controls

Electronic signatures used within these systems must uniquely identify the individual performing the action and must be permanently linked to the corresponding electronic record. Electronic signatures must be attributable to a single individual and may not be shared.

All electronic systems used for manufacturing records must maintain secure, computer-generated, time-stamped audit trails that record the date, time, and user identity associated with the creation, modification, approval, or deletion of records.

Access to electronic systems must be restricted to authorized personnel through controlled user accounts and role-based permissions in accordance with established information technology and quality system procedures.